An initial assessment should not begin with a generic cost-per-megawatt request. The same capacity can require very different infrastructure, redundancy, site works and commissioning programmes.

Minimum input set

InputWhat to define
LoadCurrent, design and future capacity; active/reactive power and profiles.
ReliabilityCategory, permitted outage, N/N+1/2N, critical loads and black start.
DutyBase/peak/standby operation, running hours, seasonality and outage windows.
FuelType, parameters, limits, backup, tie-ins and commercial metering.
SiteBoundaries, geotechnical data, existing utilities, logistics, noise, environmental and operating-site constraints.
ConnectionsUtility requirements, points of connection, voltage, protection, metering and dispatch.
PhasingHandover stages, temporary arrangements, first-power date and final readiness.
BoundaryWho engineers, supplies, constructs, tests, permits and operates.

What the first cycle can establish

  • A preliminary solution architecture and options.
  • Critical unknowns and a plan to close them.
  • A preliminary E / P / C / Cx responsibility matrix.
  • A high-level schedule and long-lead equipment list.
  • An estimate range with explicit assumptions rather than false precision.

What to attach to the Project Brief

  1. Scope or required-outcome description
  2. Single-line diagram and available utility requirements
  3. Plot plan, site boundary and existing utilities
  4. Load profile or critical-load list
  5. Target first-power and final-readiness dates