CAPABILITIES / E · P · C · Cx

An engineering system from decision to handover

Capability is not a claim: the delivery system is shown in full, while the actual MONOLIT boundary is confirmed for every contract.

01 / DELIVERY MODEL

Four workstreams under one control system

E

Engineering

Input data, surveys, technical coordination, interfaces and change control.

P

Procurement

Procurement strategy, RFQ, technical bid evaluation, expediting, FAT, logistics and incoming inspection.

C

Construction

Mobilisation, subcontractors, HSE, QA/QC, progress control, as-built records and workfront closeout.

Cx

Commissioning

System readiness, individual and integrated testing, punch lists and phased handover.

02 / PROCUREMENT

Procurement sits on the critical path

Strong procurement controls more than price. It connects technical requirements, manufacturing, vendor data, logistics, construction readiness and the installation date.

PWR

Power electrical equipment

Integrated equipment for power intake, conversion and distribution within the agreed supply boundary.

SWG

MV/HV switchgear

Indoor and outdoor switchgear with verification of single-line design, protection, interlocks and factory readiness.

LV

LV assemblies and ATS

Main and distribution boards, auxiliary panels and automatic transfer systems with coordinated fault levels and selectivity.

TRF

Transformers

Power and distribution transformers: technical evaluation, drawing review, test control, completeness and transport planning.

GEN

Diesel and gas-engine gensets

Prime, standby and emergency generation with auxiliaries, synchronisation and defined integration requirements.

CBL

Cables and busways

Power, control and specialist cables, busways, accessories and identification tied to the cable schedule.

I&C

Instrumentation and control

Field instruments, control and automation panels, interface signals and the documentation required for integration.

MECH

Pumps, heat exchangers and valves

Mechanical equipment and valves checked against duty points, materials, connections and maintainability requirements.

HEAT

Boiler and thermal equipment

Boilers, burners, pumping groups, heat transfer and auxiliary systems within one coordinated technical configuration.

03 / PROCUREMENT CONTROL

Vendor → Factory → Logistics → Site

01

Vendor Management

A supplier responsibility matrix and controlled register of communications, deviations, decisions and obligations through closeout.

02

Expediting

Manufacturing plan-versus-actual tracking, critical-operation follow-up, vendor-data control and shipment-readiness forecasting.

03

FAT / Factory Acceptance Test

An agreed procedure, witness/hold points, test records, punch list and confirmation of equipment readiness before shipment.

04

Logistics

Routing, packing, permits, insurance, delivery schedule, unloading and alignment with site readiness.

05

Incoming Inspection

Quantity, completeness, identification, damage and document checks before release to installation.

06

Document Control

MDR/VDR control, drawing approvals, certificates, data sheets, test reports and the final manufacturing record book.

03 / STAGE-GATE

Five gates for controlled delivery

G1

Qualification

Outcome, inputs, interfaces, risks and bid / no-bid.

G2

Baseline

Schedule, budget, resources, procurement, HSE, quality and reporting calendar.

G3

Mobilisation

Team, subcontractors, method statements, temporary works and workfronts.

G4

Production

Progress, change, risk, HSE/QA-QC, supply and documentation.

G5

Handover

Testing, punch list, as-built dossier and warranty framework.

04 / PROJECT CONTROL

What the owner sees in each reporting cycle

  1. 01Critical path and completion forecast
  2. 02Physical progress and plan / actual
  3. 03Critical procurement status
  4. 04Risk, decision and change registers
  5. 05HSE, quality and open punch items
  6. 06As-built documentation readiness
  7. 07Cash-flow / cost report when in scope